Center Ridge Road widening overage invoice

North Ridgeville

Summary

ODOT billed the city $3.6 million in engineering and contractor overruns on the Center Ridge widening project — mostly caused by Windstream's slow utility relocation. The city has $2.7 million set aside and is being asked for another $923,000, and officials expect to fight it, possibly in court.

At a glance

Total mentions
1
Last 30 days
0

Discussed at 1 meeting in the last 60 days; most recently Sep 21, 2026.

Impact analysis

💰Financial impact

The city is on the hook for about $923,000 now, with more change orders expected.

✅Who benefits

Nobody locally benefits — taxpayers could be saddled with costs caused by a utility's delays.

⚠️Who could be affected

North Ridgeville taxpayers, who city leaders argue should not pay for Windstream's delays.

Mentions & discussions (1)

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for North Ridgeville

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.