HighRoads

Sugar Ridge Road sidewalk/path project opposition

Roughly a dozen Sugar Ridge Road residents opposed the project's 10-foot asphalt path through front yards and the road being built to handle heavy trucks, citing privacy, trees, drainage and falling home values. Petitions with 79 and 72 signatures were submitted. City officials say no plans are final and comments are open through November 27.

2 mentions (2 this month)Last discussed Nov 2, 2026
HighRoads

Center Ridge Road widening overage invoice

ODOT billed the city $3.6 million in engineering and contractor overruns on the Center Ridge widening project — mostly caused by Windstream's slow utility relocation. The city has $2.7 million set aside and is being asked for another $923,000, and officials expect to fight it, possibly in court.

1 mentionLast discussed Sep 21, 2026
HighRoads

2026 Infrastructure and Equipment Bids

Emergency spending covers fixing a vehicle-fire-damaged street with insurance money, buying service garage repair parts, and replacing failing fuel tanks at the fire station.

3 mentionsLast discussed Sep 8, 2026
HighRoads

Sugar Ridge and Bender Road roundabout

Council approved applying for state funding for the roundabout 5-2, with Swenk voting no because she opposes the project itself. Resident Albert Krage questioned spending over $700,000 when a caution light or signage might do the job.

1 mentionLast discussed Aug 17, 2026
HighRoads

Full-depth road project delayed

Chaucer and Westfield are done; the east end of Bagley Road is next starting June 17, and state money is in hand for repaving Mills Road, possibly jointly with Avon.

2 mentionsLast discussed Jul 6, 2026
HighRoads

North-south roadway connectivity and emergency response times

The project would connect Waterbury Boulevard to the Route 83 roundabout, creating a continuous route from Sugar Ridge to Route 10 and cutting emergency response times for neighborhoods east of Waterbury. The police and fire chiefs support it, and council members discussed making the connector a truck route to divert heavy traffic from Sugar Ridge and Center Ridge.

1 mentionLast discussed Mar 5, 2026
HighRoads

Lorain Road bridge maintenance grant

The city landed a $739,000 ODOT grant for its biggest bridge — the 300-foot Lorain Road span over the Norfolk Southern tracks. Work includes fencing, curbs, joints, and possibly slabs and guardrails.

1 mentionLast discussed Jan 20, 2026